Garden Park built 83 apartments. Portland gained 54 homes.
In Powellhurst-Gilbert, a redevelopment preserved housing on an existing site. The buildings, the bond report and the neighborhood each have a different count.

- Homes on the original site
- 63
- Newly constructed apartments
- 83
- Net increase in affordable homes
- +54
At Garden Park Estates on Southeast 136th Avenue, the developer says crews built 83 apartments. The regional housing bond counts 54 additional homes. The completed complex has 117. All three figures describe the same site. The missing piece is the housing that stood there before the work began.
Garden Park began with 63 homes. Innovative Housing, Inc., which redeveloped the property, says 34 existing units were retained and renovated. That leaves 29 original homes replaced during construction. Of the 83 newly built apartments, the first 29 brought the site back to its previous capacity. The remaining 54 expanded it. Someone counting construction would record 83. A neighbor asking how many more households could live on the site would count 54.
There was a gain inside the buildings, too. Innovative Housing says the renovated homes received fixtures and building-system improvements comparable to the new apartments. All units received air conditioning with Portland Clean Energy Fund support. The completed site includes three common laundry rooms and space for resident services. Twenty-five of the apartments are designated for permanent supportive housing. Oregon Housing and Community Services supports rental assistance and services, and Innovative Housing identifies its own housing stability and peer-support specialists as part of the program.
The financing record also needs a date. Metro’s 2025 annual report listed $2,239,308 in regional housing bond funds for Garden Park. Its July–September 2026 progress report lists $4,189,308 and marks the project complete, a difference of $1.95 million between the published figures. The project profile still gives the rounded earlier figure of $2.2 million. The two tables establish what Metro reported at each point. They do not itemize the change or document a payment to the developer.
A separate Metro decision explains what preserving affordability can mean after construction. The regional government says it approved funding to keep reduced rents in place for 29 Garden Park apartments. The public announcement identifies the tenant benefit but gives no property-specific dollar amount. Matching that approval to the change in the bond table would require the underlying agreement.
Portland’s Housing Bureau announced completion in April, and the developer says all buildings were complete in March 2026. For tenants the end result is one address with a larger supply of affordable apartments. For readers following the bond, Garden Park is a reminder to record both how many homes an investment adds and how many existing homes it carries forward.
How we checked this
We compared the developer’s construction scope with Portland’s total apartment count, then matched the Garden Park row across two Metro bond reports. Metro separately confirmed the rent-preservation award. The public summary gives the number of apartments covered. The exact amount of that specific award and its payment history remain open reporting questions.
- Innovative Housing · construction scope, funding and services
- Portland Housing Bureau · completion notice
- Metro · Garden Park project profile
- Metro · 2025 annual report, financing table
- Metro · July–September 2026 bond progress report, Portland table
- Metro · award to maintain reduced rents on 29 Garden Park apartments