The 17 months before 73Foster broke ground

An early bond approval and the finished building tell the same story about the length of construction. The calendar slipped before the first month of work.

Architectural study model with a lifted façade and exposed floors.
Editorial illustration · Tryon Media Group
Shift in the construction start
17 months
Construction span in both timelines
13 months
Apartments completed
64

The public record for 73Foster has three different dates a neighbor might reasonably call the finish. Metro records construction ending in July 2026. Portland’s Housing Bureau announced in August that the apartments had opened. The ribbon cutting took place in November. To understand how long it took to build these 64 homes on Southeast Foster Road, start with the first of those dates and turn back to the original funding decision.

In an approval published with its first-quarter 2024 bond report, Metro expected construction to begin in January 2024 and end in February 2025. The dates in its completed-project profile are June 2025 and July 2026. Both pairs span 13 months. The start shifted by 17 calendar months, and the finish moved by the same amount. By the time the contractor began work, the entire difference between the two schedules was already visible.

A funding amendment explains one part of the wait. Metro reported that REACH Community Development had encountered difficulty converting another property, Renaissance Commons, to permanent financing. REACH could no longer put a previously pledged $541,000 sponsor loan into 73Foster. Insurance and security costs also rose. The amendment approved another $200,000 in Metro supportive-housing pilot funds. Portland announced the financial closing in June 2025. These records explain a documented financing hurdle while leaving the duration of its individual effects unresolved.

Different public dollars followed different jobs. Metro identifies $4.4 million in regional housing bond funding for construction and a $1.5 million Portland Clean Energy Community Benefits Fund grant. Multnomah County and the state supported services for people moving into 22 apartments reserved for households leaving homelessness. REACH developed the property, APANO assisted with leasing and resident services, and Community Vision helps connect people with disabilities to the housing.

For the next development on a council agenda, the revealing dates to write down are the expected start and finish on the day money is approved. Keep them even when officials publish a new forecast. At 73Foster, that simple comparison locates the 17-month shift far more precisely than the date on the ribbon.

How we checked this

We matched the named project in Metro’s first approval to its completed profile. Each duration is the difference between published calendar months. The records give month-level precision. Public funding amounts describe the stated financing or approval.